The Minister of Public Works, Abdel Qader Jlaoui, confirmed that the pace of completing the Eastern Mining Line project has significantly accelerated. To date, 174 kilometers out of the total 422 kilometers of the project have been completed. Data indicates that the work includes 60 bridges and 12 tunnels, with a target to complete 127 kilometers of the sections before the end of September, including the sections from Annaba to Bouchkourf, Draa Ben Khedda to Wadi Al-Kabir, and Tébessa to Ténoukel. The minister emphasized the importance of intensifying coordination between the construction companies and local authorities, ensuring the achievement of milestones within the set deadlines, and monitoring the progress of work, which involves excavation, leveling, and track installation, all aimed at completing this strategic project on time.