Tiaret Governor Abdelwahab Bertima reviewed the status of development projects for 2024–2026, aiming to address delays and obstacles. Fifty-nine of the 60 projects in the 2024 programme have been completed, as have 56 of the 70 projects in the 2025 programme. Of the 53 projects registered for 2026, 28 are underway, four are suspended, and five have yet to begin. The meeting also reviewed health-sector indicators, including 34 clinics operating around the clock and medical staffing levels. The governor directed officials to improve the reception of patients and follow up on the causes of project delays, and discussed allocating land for a university hospital complex.