A coalition comprising Siemens Electric and Sinohydro has signed a contract valued at approximately $2.2 billion to expand Rabigh 2 Power Plant in Saudi Arabia, making it one of the largest gas-fired combined cycle projects in the region. The project aims to add 2.3 gigawatts of electricity to meet increasing demand and support industrial, commercial, and residential growth across the Kingdom. Commercial operation is expected to commence in May 2029. The alliance is responsible for designing and executing civil works, supply, installation, and commissioning for the project, which will include six Siemens gas turbines and two steam turbines.