The concrete slab work for the fourth level of the internal containment vessel at Unit 1 of the Dabaa Nuclear Power Plant has been completed, using 1,608 cubic meters of concrete over 30 continuous hours with the participation of about 160 specialists throughout the day. This effort aims to raise the height of the reactor building from +24.400 meters to +34.000 meters. This achievement reflects significant progress in the project's implementation and ushers in a new phase of installing the fifth level, further advancing the plant's continuous development. The authority is committed to high quality and international nuclear safety standards, affirming that this success contributes to Egypt's efforts to diversify energy sources and achieve sustainable development.