The work teams at the Dabaa Nuclear Power Plant project successfully installed the reactor’s bottom head in Unit 3. This is a crucial component of the VVER-1200 pressurized water reactor system, weighing 130.85 tons and measuring 3.82 meters in length. The installation marks an important step in preparing the reactor and brings the unit closer to the assembly of the reactor pressure vessel, which weighs 320 tons and extends up to 13 meters in length. The achievement aims to ensure that all work is completed according to the scheduled timeline while adhering to quality and nuclear safety standards.