The first phase of Line 4 of the metro will be operational in the first half of 2027. This phase spans 19 kilometers and includes 17 stations from the west of the 6th of October Ring Road, passing through the Grand Egyptian Museum, then Raml Square, Al-Haram Street, and Giza, where it intersects with Lines 1 and 2 of the metro. The line is planned to consist of four phases, with a total length of up to 101 kilometers, featuring 58 stations and an expected capacity to serve approximately two million passengers. This will help reduce pressure on the road network and facilitate mobility between different areas. To date, six trains out of a total of 23 supplied by Mitsubishi Corporation have been delivered, with construction and electromechanical work carried out by specialized Egyptian companies.