The Ministry of Public Works is implementing infrastructure works in the Qartaba area under a contract that spans three years, beginning April 2024. Significant progress has been made, with the actual completion rate reaching 82% thus far, compared to 75.5% as per the approved schedule. The works include a sewage network at 97%, stormwater drainage at 97%, a telephone network at 99%, street lighting at 96%, as well as asphalt layering at 78.9% and asphalt paving at 15.2%. The project is expected to be completed as scheduled by April 2, 2027.