Construction work is continuing on Phases Two and Three of Kuwait’s North Zour project, which will add 2,942 megawatts of power generation capacity and produce 120 million imperial gallons of water. The company is nearing completion of the financial close. The project comprises four gas units with a total capacity of 2,044 megawatts and two steam units with a total capacity of 900 megawatts, along with seawater intake works, the expansion of a 400-kilovolt substation, and the construction of control and instrumentation buildings. The gas units are scheduled for completion in the second quarter of 2029, with the steam units and full commercial operations expected to be completed and commenced, respectively, in the fourth quarter of the same year.