Mellehita Company successfully executed an innovative technical operation to supply the Al Ruwis Power Station with natural gas via a reverse feeding method from the Mellehita complex, aiming to support the stability of the power grid. The initial pumping rate reached approximately 25 million cubic feet per day, with the potential to increase to 100 million cubic feet. This allowed for the shutdown of diesel fuel turbines and their operation with natural gas at a capacity of 100 MW, enhancing operational flexibility and reducing liquid fuel consumption. This achievement resulted from exceptional technical efforts by engineers and technicians, and it provides gas supplies to power plants with a total capacity exceeding 750 MW. It underscores the National Oil Corporation's commitment to maintaining grid stability and improving operational efficiency.