Militah Oil and Gas Company completed the installation and operation of new gas compressors on the Sabratah gas platform in just 30 hours, reflecting high efficiency and outstanding technical expertise. The project contributes to maintaining reservoir pressure and increasing gas production by approximately 28 billion standard cubic feet annually, along with increasing condensate production by about 360,000 barrels per year. The goal is to enhance the sustainability of the field's resources and provide energy to power plants. The operation involved technical procedures to ensure system stability and continuous supply without interruption, supporting the stability of the electricity grid and increasing the amount of gas allocated for various uses.