The Libyan General Electricity Company announced the restoration of electricity after completing emergency maintenance work on the cable at the Tareggen transformation station. Over the past few days, urgent repair work has been carried out at the station. Additionally, the new South Tripoli station is nearing completion, with 98% of the work finished. The first unit is expected to be commissioned in the coming days, with a capacity of 1,320 megawatts. The project is being carried out by the Turkish company Galick, while German company Siemens is responsible for supplying the equipment.