Al-Brega Oil Marketing Company announced that it is ready to supply fuel to the South Tripoli Power Plant in preparation for the trial operation of its first unit. The company confirmed that it has secured 21,550 cubic meters of fuel during July and is working to complete the remaining amount to reach 36,000 cubic meters. Officials also indicated that natural gas supplies are stable at approximately 135 million cubic feet per day, supporting the plant's electricity generation capacity of up to 1,320 megawatts. The project is 98% complete. Continuous coordination among the relevant authorities aims to ensure the success of the operational tests and the stability of the regional power grid.