The General Electricity Company announced the completion of the commissioning and preparation work for the 400/220 kV South Tripoli Substation, as part of the new South Tripoli Power Plant project. The project is carried out by the Turkish company Jalk and the German company Siemens. The scope of work includes the supply and installation of two 400 kV generator bays, as well as the development and programming of protection and control systems (SCADA), along with necessary technical testing. The substation serves as a strategic link, enabling the transfer of energy produced by the new power plant to the national grid at both 400 kV and 220 kV levels. It supports the stability of the electricity network in Tripoli and its surrounding areas. This phase marks an important step in enhancing the grid's capacity to receive and distribute power, thereby contributing to reducing the load on the current network and improving the stability of power supply.