The General Electricity Company of Libya announced the completion of a major milestone in the new South Tripoli power station project. The step involved loading the step-up transformer and connecting it to the 400-kilovolt station, enabling the transition to testing and commissioning phases. The current phase focuses on verifying the readiness of control and protection systems, as well as voltage and frequency stability, prior to the full startup of the station. This effort aims to enhance generation capacity, achieve electrical grid stability, and provide a reliable supply to citizens.