The planned railway project will link Nador to Oujda via Berkane, with a 142-kilometre electrified double-track line, as well as a 26-kilometre branch from Berkane to Saïdia. Its estimated total cost is 18.628 billion dirhams. The proposed route will pass through Selouane, Al Aaroui, Zaio, Aklim and Bougriba before reaching Berkane, then continue through Ahfir and Beni Drar to Oujda. It will include a 6.52-kilometre twin-bore tunnel and around 30 kilometres of bridges and other engineering structures. The line will carry passengers at speeds of up to 160 kilometres per hour and freight at up to 80 kilometres per hour. The southern corridor was selected after a technical, environmental, economic and social comparison of two possible routes.