The integrated residential neighborhood projects known as “Sorouh” in Al Dakhiliyah Governorate, with investments of approximately OMR 76.9 million and a total of 1,919 units, had completion rates ranging from 11% to 95% at the end of October 2026. Completion stood at 90% in Al Noor in Nizwa, 95% in Sama in Bahla, 30% in the first phase of Hisn Al Zain in Bidbid, and 11% in each of Namaa in Izki and Al Muzn in Samail. Sales reached 100% in Al Noor and Sama, and 95% of the units in the first phase of Hisn Al Zain, compared with 44% in Namaa and 40% in Al Muzn. The initiative aims to provide suitable housing for eligible beneficiaries and shorten waiting lists. The first phase of Hisn Al Zain is expected to be handed over in 2027, with the Namaa and Al Muzn phases due in 2028.