The President of the Public Works Authority (Ashghal), Mohammed bin Abdulaziz Al Meer, inspected the South Doha Sewage Treatment Plant project and reviewed progress, which has reached approximately 65%. He stressed the need to adhere to the project timeline and to quality and safety standards. The project, being delivered through a public-private partnership, represents an investment of QAR 6.3 billion and is expected to be completed in the second quarter of 2028. Its first phase will treat 150,000 cubic metres of wastewater per day, serving more than 300,000 people, with the capacity to expand to 600,000 cubic metres per day. The project includes the reuse of treated water and energy recovery. The developer will operate and maintain the plant for 25 years.