مباشر
مباشر
Ready to play
Ready to play
The National Glass Industries Company (ZAG) announced the restart of a damaged production line following a limited fire incident, after completing repairs that took approximately ten months. The downtime period from September 2025 to July 2026 resulted in total costs of 16.1 million Riyals, which were covered by insurance. The repairs involved technical and logistical reasons that led to increased costs, as the damage repairs and spare parts procurement exceeded initial estimates for the original requirements. Additionally, evaluations showed that the extent of equipment damage was greater than initially anticipated, causing an extension of the downtime and delaying the resumption of production. This event reflects the operational challenges the company faced and has impacted its financial results, notably with a decrease in profits of around 16.1 million Riyals due to the production halt during the period from September 2025 to July 2026.