Work on the expansion of the capital’s southern entrance is progressing across five sections, with completion rates of 63%, 96%, 91%, 99% and 53%. The project’s final phases are expected to be completed by the end of 2027. Meanwhile, demolition of the old bridge at Lacania is being completed, and the road surface is being reinforced in both directions in coordination with the traffic police. The main challenges involve relocating water, electricity, gas and telecommunications networks. Around 1,200 telecommunications units were relocated before 2025, and a further 600 this year; approximately 800 units are still awaiting relocation. The project director urged road users to be patient and obey speed limits and traffic signs, stressing that work is ongoing and that efforts are being made to minimise its impact on traffic.