The Tunisian Company of Electricity and Gas began preparing for summer 2027 in September 2026, with plans to be ready by June. The projects include 300 megawatts of battery storage, gas-engine power plants with a capacity of 200 megawatts, 300 megawatts of solar power, and the reopening of the 300-megawatt Borj El Amri plant in late 2026. The company has also scheduled the construction of a third unit at Borj El Amri for 2027–2028, alongside efforts to improve demand management during peak hours and raise awareness about conserving electricity. These measures come amid calls for better coordination to prevent a repeat of last summer’s outages. A survey of 325 exporting companies found that 89.2% rely on electricity, and that outages had harmed production at 73.8% of them. Unannounced outages accounted for 79.7%.