Sharjah Electricity, Water, and Gas Authority has implemented developmental projects to enhance the electricity networks in Kalba city, aiming to increase efficiency and meet the growing demand for energy. The projects included the construction of two 33-kilovolt distribution stations and network expansion, with 80% completion achieved in the network extension project in Jabal Al Daim at a cost of 15.4 million AED, and 22% progress in establishing a station in the same area at a cost of 89 million AED. The work also involves upgrading the network in New Kalba Industrial Area by 54%, replacing old distribution boxes, and other distribution stations, with investments reaching up to 44 million AED. These projects aim to improve the quality and reliability of electricity supply and support the city's future development.