The Minister of Public Works and Basic Infrastructure, Abdelkader Jeloui, conducted an unscheduled night tour to oversee the progress of the expansion works at the Annaba Phosphate Port, which includes the construction of a mining quay as part of the integrated phosphate project. The visit revealed an acceleration in the pace of work, with 656 out of 1,332 piles driven, a stone barrier completed, and sand being dredged at a rate of 30,000 cubic meters per day. Additionally, preparations are underway for the infrastructure of precast slabs. The minister emphasized the importance of intensifying monitoring and coordination among all stakeholders to complete the project within the designated timeframe, in accordance with the planned schedule.