A visit by Minister of Public Works, Abdelkader Jlaoui, to the Annaba phosphate port expansion project indicated that work is progressing very rapidly. Approximately 680 piles have been driven out of the planned 1,332, and around 1.2 million cubic meters of marine fill have been completed using dredging ships. The seawall has also been reinforced and its resistance to waves improved, employing new techniques for controlling soil settlement and increasing its bearing capacity—techniques being applied for the first time in Algeria. The minister ordered an intensification of field monitoring and enhanced coordination to ensure the project's completion within the scheduled timeframe.