The trial operation of Alexandria Metro is scheduled to begin in March 2027, as part of a project to develop the public transportation system in the governorate. The first phase of the project spans 21.7 kilometers and includes 20 stations, of which 6 are at ground level and 14 are elevated. It connects Abu Qir Station with Misr Station. The project aims to increase capacity from 2,850 to 60,000 passengers per hour and improve transit speed, with an expected reduction in travel time by half, activation of trains running at speeds of up to 100 km/h, and decreasing headway from 10 minutes to two and a half minutes. The project duration is 38 months, and it involves the manufacturing of 21 trains within the Egyptian National Company for Rail Industries.