The Ministry of Public Works and Housing completed a 150-metre temporary bypass on the Al-Rama–Al-Joufeh road in less than three days, after the main road was closed because of cracks near the bridge, to ensure residents could get around. The bypass has six pipe culverts and is for local traffic only; trucks are prohibited. It may be temporarily closed when water flows over it. The ministry will begin building a new box culvert to replace the old bridge.