The report from the Ministry of Public Works indicates that the infrastructure project in the Yarmouk area is making significant progress, with an actual completion rate of 92% of the total work, despite the scheduled timeline estimating only 72% completion at this point. The sewer and stormwater drainage networks have been fully completed at 100%, while the phone and lighting networks have reached 97% and 98%, respectively. Currently ongoing work includes asphalt paving in certain sections, with all other major tasks already completed. This project is part of a three-year plan that began in April 2024.