The Kuwaiti Ministry of Public Works confirmed that infrastructure works in the Yarmouk area have reached an actual completion rate of 92%, with sanitary sewer and rainwater drainage networks completed at 100%. According to the schedule, the targeted progress was 72%, and work is currently ongoing to complete remaining tasks such as telephone and electricity networks, which have exceeded 97%. These efforts are part of the area's development plan and contribute to fully enhancing its services and infrastructure.