The General Authority for Roads has resumed work on the final phase of the project linking Al Sail Al Kabeer Road with the Riyadh–Taif Road, following the completion of the relocation of utility infrastructure that conflicted with the project. The project is 72% complete, with 22.7 kilometers finished out of a total of 24.7 kilometers. The remaining work is concentrated in the two-kilometer connection section, the secondary roads, and the construction of an underpass. Once completed, the project is expected to make travel easier for pilgrims and trucks, ease traffic congestion, and reduce journey times.