On November 11, 2026, Al Jouf Agricultural Development Company approved bids for a project to connect its facilities in the Basita Center in the Al Jouf Region to the electricity grid, with a total value of SAR 398.43 million, excluding VAT. The project covers four areas: the internal electricity network, external interconnection cable lines, and engineering supervision and contract management for each. It is part of a program aimed at replacing liquid fuels. Work is scheduled to begin before the end of the fourth quarter of 2026 and take approximately 13 months.